0 [{"id":224828,"quiz_id":"13250","answer_id":null,"answerType_id":"3","created_at":"2017-06-22 11:38:43","updated_at":"2017-06-22 11:45:07","questionName":"write out the order of Tasks and processes in the Planning Process Group","questionTimeSeconds":"0","questionTimeMinutes":"20","questionImagePath":null,"position":0,"explanation":"","question_score_id":null,"lang":null,"questionAudioPath":null}]
224828
0
1200
block

write out the order of Tasks and processes in the Planning Process Group

Match the text (click and drag)   

(0/0)




Match the Text

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

Click and drag

Perform risk identification, qualitative and quantitative risk analysis, and risk response planning

Develop schedule

Determine how you will plan for each knowledge area

Create network diagram

Determine detailed requirements.

Gain formal approval of the plan

create change management plan

Develop realistic and final PM plan and performance measurement baseline

Finalize how to execute and control all parts of PM plan

Estimate resource requirements

Develop budget

Plan communications and stakeholder engagement

Create process improvement plan

Create activity list

Determine critical path

Determine quality standards, processes and metrics

Determine planning team

Create WBS and WBS dictionary

Assess what to purchase and create procurement documents

Estimate time and cost

Go back (iterations)

Hold kick off meeting

Finalize procurement documents

Determine all roles and responsibilities

Create project scope statement