[{"id":278552,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 18:53:12","updated_at":"2017-09-16 22:11:10","questionName":"The customer has accepted the completed project scope. However, the lesson learned required by the project management office have not been completed. What is the status of the project","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":1,"explanation":"","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278560,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:12:59","updated_at":"2017-09-16 22:11:11","questionName":"Which of the following BEST describe the project manager's role as an integrator:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":9,"explanation":"Integration refers to combining the activities, not team members. ","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278564,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:19:58","updated_at":"2017-09-16 22:11:11","questionName":"Which of the following BEST describes a project management plan:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":13,"explanation":"The project management plan includes more than just a bar chart and the project manager's plan for completing the work. It includes all the management plans for the project.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278559,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:10:55","updated_at":"2017-09-16 22:11:11","questionName":"Integration is done by the:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":8,"explanation":"Integration is a key responsibility of the project manager.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278551,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 18:50:29","updated_at":"2017-09-16 22:11:10","questionName":"The need for _______ is one of the major driving forces for communication in a project.","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":0,"explanation":"The project manager in an integrator. This is a question about your role as an integrator and communicator","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278558,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:10:01","updated_at":"2017-09-16 22:11:11","questionName":"Effective project integration usually requires an emphasis on:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":7,"explanation":"This question is asking for the most important of the choices. Think about what is involved in integration: project manager plan development, project management plan execution, and integrated change control. Updates an product control are parts of project","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278563,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:17:51","updated_at":"2017-09-16 22:11:11","questionName":"Which of the following BEST describes what a project charter may be used for when the work is being completed?","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":12,"explanation":"One of the ways to decide if a change should be approved is to determine whether the work falls within the project charter. If not, it should be rejected, assigned to a more appropriate project, or addressed as project of its own.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278562,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:15:19","updated_at":"2017-09-16 22:11:11","questionName":"Double declining balance is a form of ","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":11,"explanation":"","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278565,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:22:44","updated_at":"2017-09-16 22:11:11","questionName":"Which of the following is TRUE about the development of a project charter?","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":14,"explanation":"The project manager may create the project charter, but it is approved and authorized by the project sponsor, giving the project manager authority to proceed with the project.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278557,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:05:53","updated_at":"2017-09-16 22:11:11","questionName":"A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary?","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":6,"explanation":"The sponsor issues the project charter and so he or she should help the project manager control changes to the charter. The primary responsibility lies within the sponsor.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278556,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:03:58","updated_at":"2017-09-16 22:11:11","questionName":"A work authorization system can be used to:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":5,"explanation":"Who does each activity is manged with the responsibility assignment matrix. When each activity is done is managed with the project schedule. A work authorization system is used to coordinate when and in what order the work is performed so that work and pe","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278553,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 18:55:21","updated_at":"2017-09-16 22:11:10","questionName":"When it comes to changes, the project manager's attention is BEST focused on","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":2,"explanation":"Project managers should be proactive. The only proactive answer here is preventing unnecessary changes.","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278561,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:14:06","updated_at":"2017-09-16 22:11:11","questionName":"Approved corrective actions are an input to which of the following process:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":10,"explanation":"","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278554,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 18:58:53","updated_at":"2017-09-16 22:11:10","questionName":"The customer on a project tells the project manager they have run out of money to pay for the project. What should the project manager do FIRST?","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":3,"explanation":"Every project must be closed, as closure provides benefit to the performing organization. This means simply stopping the work is not the best choice. Shifting work and release team members do not solved the problem - they just postpone dealing with it. T","question_score_id":null,"lang":null,"questionAudioPath":null},{"id":278555,"quiz_id":"14599","answer_id":null,"answerType_id":"0","created_at":"2017-09-16 19:00:58","updated_at":"2017-09-16 22:11:10","questionName":"All of the following are a parts of an effective change management plan EXCEPT:","questionTimeSeconds":"0","questionTimeMinutes":"2","questionImagePath":null,"position":4,"explanation":"A change management plan includes the processes and procedures that allow smooth evaluation and tracking of changes. Lesson learned are reviews of the processes and procedures after the fact, to improve them on future project.","question_score_id":null,"lang":null,"questionAudioPath":null}]